Below lists the key activities of any BAGM project. Please note that our standard working days are Monday through Thursday. To visualize the full timing and flow of your project, we encourage you to review our Project Calendar.
Before your project is created, you must first Design Your Project with our team. This step includes material selection, layout decisions, and collection of all necessary details to ensure your project runs smoothly.
Minimum 9 working days before template
6–8 working days before template
Understand that design changes after this point may cause delays or extra charges.
3 – 5 working days before template
2 days prior to template
6 working days before installation
The template is a key step in BAGM’s project process. Using a precision laser, we create a precise digital drawing of your project. Our technician reviews all design details on-site to confirm accuracy. Occasionally, site conditions may require minor adjustments to the design or timeline.
5 working days prior to installation
4 – 2 working days before installation
2 days prior to install
Installation is the most exciting step in your BAGM project. By this stage, all design decisions have been finalized, and our skilled installation technicians bring your vision to life.
Your involvement is essential throughout the design, template, and preparation phases. Once installation begins, our team takes it from there — ensuring a smooth, professional finish.
1 working day post installation
If you have any questions or areas of concern, contact your Project Manager. A phone call is always welcome; however, email is the preferred method for reporting issues, as it allows your project manager to review details and provide a solution more efficiently. Please include the following information to help us troubleshoot promptly: